All sanitary sewer projects are handled on a project specific basis, however, the typical steps and the normal order of these steps are as follows:
1. Application for Preliminary Sewage Service Agreement; 2. Execution of Preliminary Sewage Service Agreement; 3. Determination of availability of service and estimate of escrow and set-aside amounts, if appropriate. If the project is in accordance with municipal planning, then the review process continues as follows: 4. Sewer design review and approval; 5. Execution of Final Sewage Service Agreement and Set-Aside Agreement; 6. Shop drawing review; 7. Preconstruction meeting; 8. Construction/Inspection; 9. Testing, punch list completion and Flow Release Forms; 10. As-built drawing and easement description review; 11. Dedication Documents review and approval; and, 12. Acceptance for dedication.
|